The county published a progress release on Oct. 28 for the fire station and sheriff’s operations center it is building in the Silverleaf area. The release describes a nearly 20,000-square-foot shared facility for Fire Rescue and the Sheriff’s Office in the north-central part of the county. It states that the project remains on schedule, with construction completion targeted for late 2026 and final completion anticipated in early spring 2027. A county release of May 2, 2025 gave the same station an estimated completion date of 2026, and both of those sentences are printed here with their dates.

The station is the second of six buildings in a program the county has described as a five-year public safety plan announced in April 2024. That plan is four new fire stations and renovations to two existing ones, and the May 2025 release is the only document this paper has found naming all six. It gives a date for each of them, which is the part of the program this paper has not reported before.

The four new stations, and the two with no cost

The four new stations are 21 at Flagler Estates, 22 in the Silverleaf area, and 23 in the Beachwalk and Twin Creeks region off County Road 210. The fourth is 24 in the Long-Leaf Pine and Roberts Road area, which that release estimates for completion by the end of 2030. Station 23 is estimated in the same release for completion by the end of 2028, which makes it the next of the four. None of the releases cited here gives a cost for either Station 23 or Station 24, and this paper has found no published figure for either one.

The two renovations are Station 17 at 10001 Cartwheel Bay Avenue off County Road 210 west, first put into service in 1990 as a volunteer station. The second is Station 10 at 155 Library Drive in Ponte Vedra Beach, first placed into service in 1985, also as a volunteer station. That release gives the Station 10 design as beginning after Oct. 1 and its construction as scheduled to start in 2027. It also says there will be no reduction of staffing or services during the work, and that response times of approximately five minutes to 911 calls will be maintained.

The stated reason for building the four is coverage, because the release says the stations will improve fire coverage for properties outside a five-mile radius of an existing fire station location. It adds that this will help with residential and commercial insurance, which is the only consequence for a household that the release names.

The first of the six opened on Saturday

The first of them opened at Flagler Estates on Saturday, Oct. 24, at 4630 Melanie Street in Hastings. This paper reported that opening on Oct. 24, together with the three different costs the county has published for that one building. The February 2025 contract award gives $4,001,674, the March 2025 groundbreaking release gives $3.8 million, and last week’s advisory gives $4.5 million. Both 2025 releases said that building would be finished by the end of that year, and the ribbon was cut about ten months after that.

Station 22, and the figures that have held

Several of the Station 22 figures have not moved at all across three releases published eighteen months apart. The approximately $13 million cost is the same figure in the March 2026 release and in the October 2026 release. The approximately 20,000 square feet is the same in May 2025, in March 2026 and in October 2026. The complement of approximately 33 firefighters across three shifts, eleven to a shift, is the same in all three of those releases. The apparatus list has grown by one item, from a tanker, engine and ladder truck in May 2025 to five vehicles in the two later releases.

Two details about Station 22 did change between March and October of this year, and both of them concern where the station sits. In March 2026 the roads the station would serve were given as County Road 210 and State Road 16A. In October 2026 they are given as County Road 2209, County Road 210 and State Road 16, which is three roads rather than two. The October release also states that the location will offer access to the future First Coast Expressway, which the March release does not mention.

The Sheriff’s Office portion of Station 22 is described the same way in both releases, as space for the Criminal Investigations Division. Both say the move will let detectives work from the new center rather than from their workspace near the county detention facility, and neither gives a number.

Station 22 broke ground on March 12, 2026, according to the release the county published a week after that date. On the county’s own published schedule the next of the six is Station 23, by the end of 2028.

A criminal charge is an accusation. All defendants are presumed innocent unless and until proven guilty. The Tattler tracks the cases it reports and publishes the outcome, including when charges are dropped or reduced. If you are named in this story and the case has resolved, write to corrections@stjohnstattler.org and we will update it.